Scheduled for September 16, 2024 at 7:00 AM – September 17, 2024 at 4:00 PM
Affects
Locations
Under maintenance from 7:00 AM to 4:00 PM
Paris
Under maintenance from 7:00 AM to 4:00 PM
Completed
September 17, 2024 at 4:00 PMCompleted
September 17, 2024 at 4:00 PMMaintenance has completed successfully
In progress
September 16, 2024 at 7:00 AMIn progress
September 16, 2024 at 7:00 AMMaintenance is now in progress
Planned
September 16, 2024 at 7:00 AMPlanned
September 16, 2024 at 7:00 AMOur datacenter provider, Digital Realty, will be doing maintenance on their UPS (which provides power backup if a power outage occurs until generators can start). No customer impact is expected.
Planned Work Window: 16/Sep/2024 09:00:00 CEST - 17/Sep/2024 18:00:00 CEST
Description of Works: PAR03 UPS Process : Replacement of internal batteries at end of life.
Work Type: Scheduled Repair
Risk Level: Critical
Impact: MEDIUM IMPACT works (Level 2)
During Works: No impact expected however redundancy reduced
Details: UPS process will be switching off during the opération and TB09 will be powered by the back up supply from TGBT ENVR A (TG EA)